Construction Update
- January
- Bank Financing Closed - Bank of America
- Century Construction Released to Begin Construction
- Mechanical and Electrical Drawings Completed
- Buildling Permitting Process Underway
- February
- Pre-construction Meeting Planned
- Sitework to Resume
- Pray for Dry Weather
- Pray for Permitting Process
- March
- Underground Utilities and Foundations
Photos of Site Work
Below are pictures of the progress being made on our Building Expansion. Crews have already cleared the land for construction. IBC held its official Groundbreaking service on October 29th, 2006! Construction is expected to begin in January, 2007 and to be completed by November-December, 2007.

(Oct 3, 2006) - Ground clearing and tree removal on the land for the new building. View from the existing Educational Building looking out to Courtyard Rd.

(Oct 3, 2006) - Trees on the land for the new building waiting to be cleared.

(Oct 3, 2006) - Another picture of crews working.

(Oct 29, 2006) - Pastor Mark at the official Groundbreaking Service.

(Oct 29, 2006) - Pastor Mark along with the Building Committee breaking ground.

(Jan 2, 2007) - View from Iron Bridge Road of the cleared site.

(Jan 2, 2007) - A closer picture of the building site with an erected sign announcing the expansion.

(Feb 22, 2007) - More activity being done on the construction site. A visible "Century Construction" sign now faces Route 10.

(Feb 22, 2007)

(Jul 2, 2007) - The steel framework for the new Worship Center at Ironbridge Church rises into the sky.